Halden Forecourt

Water steps down 1.8 m across nine granite treads and audibly marks the walk from the street to the library door.

A courtyard water feature seen from above, set into paving.

The problem

A public forecourt in Copenhagen has roughly ninety frost days. Standing water in a stone channel through a freeze–thaw cycle does not crack the stone; it lifts the bedding, opens the joints, and two winters later the channel leaks into the basement car park below.

What we changed

The whole installation empties. A buried 30 m³ surge tank sits under the lower terrace, and the channel drains to it in six minutes flat — we sized the outlet for that figure, because anything slower means the controller cannot react to a forecast overnight frost within a single evening closing window. Below 3 °C on a rising forecast, the system runs down and stays down. It comes back up on its own when the ten-day forecast clears.

The channel invert has a trace heater in it, not to run the water in winter — that would be indefensible — but to stop the last 2 mm of residual film from freezing into the joints. It draws 340 W and runs perhaps 200 hours a year.

Five winters on

Joints were re-pointed in year three on two treads at the lower end, where the drainage fall was 0.4 per cent instead of the specified 0.8. That is a construction defect we should have caught on the survey. Nothing else has been touched. The library counts 190 days of operation a year and has never once asked us why it is off.

Installation record

Client
Halden Public Library
Location
Copenhagen, Denmark
Year
2020
Discipline
Rill and step cascade
Type
Rill
Water volume
27 m³
Status
Completed, five winters observed